Nature’s Peace Community Playground and Picnic Area Project Teresa Dionne MGMT 404 Project Management DeVry University Online February 26, 2013 TABLE OF CONTENTS Executive Summary ………………………………………………………………. …... Page 3 Scope Statement …………………………………………………………………….

… Page 4 Work Breakdown Structure …………………………………………………………....

Page 5 Network Diagram …………………………………………………………………. ….. Page 6 Risk Management Plan ……………………………………………………………. …. Page 10 Resource Management Plan ………………………………………………………….

.. Page 14 Communication Management Plan …………………………………………………… Page 15 References …………………………………………………………………………..

… Page 16EXECUTIVE SUMMARY Nature’s Peace Community has contracted us to provide project management for a playground and picnic area for the local neighborhood. The goal is to design and build a playground and picnic area for the neighborhood using HOA fees that the neighborhood have agreed to spend no more than a total of $100,000. 00 for the community to enjoy. The lot is one half acre of cleared land that is flat and in the center of the neighborhood.

The Homeowner’s Association would like to have 4-6 picnic tables and a large playground on rubber mulch with a separate area for swing sets meant for young children and adults.SCOPE STATEMENT Project Objective To develop a playground and picnic area on the 1/2 acre lot in the community within 12 months, costing no more than $100,000. 00 Deliverables 1. Playground a. Climbing steps/wall b. Slides c.

Swing sets 2. Picnic Area a. Picnic Tables b. Trash Cans c. Outdoor Barbecue Grill Milestones 1. Project Design Started - March 1, 2013 2.

Project Design Completed - March 31, 2013 3. Project Approved by HOA - April 15, 2013 4. Permits approved - May 15, 2013 5. Equipment purchased - May 31, 2013 6.Equipment installed - August 31, 2013 7. Final Review by HOA - September 31, 2013 Technical Requirements All equipment must be secured in place and checked for safety.

The equipment needs to be clean and durable to withstand multiple children playing on it at one time. The picnic equipment needs to be durable and the barbecue grill needs to be a safe distance from the playground area. Limits and Exclusions 1. The playground and picnic equipment will be property of the HOA and they will agree to set up. 2. HOA will be responsible for upkeep and maintenance.

. The contractor is responsible for subcontracted work. 4. Work site hours limited to Monday through Friday, 8:00 A. M. to 5:00 P.

M. Customer Reviews HOA Board Members will be conducting reviews on our process, timeliness, and cost considerations in the completion of their community playground and picnic area. WORK BREAKDOWN STRUCTURE The following Work Breakdown Structure or WBS Gantt Chart provides a snapshot of the project and it indicates what the project objectives are and when they will be performed by both internal and external project team members.This shows that the project completion is to be completed before the date that Nature’s Peace Community’s Playground and Picnic Area. WBS| Task Name| Duration| Start| Finish| 1| Nature's Peace Playground ; Picnic Area| 141 days| Fri 3/1/13| Fri 9/13/13| 1. 1| Start Project| | | | 1.

2| Meeting with HOA Board| 3 hrs| Fri 3/1/13| Fri 3/1/13| 1. 3| Design Playground| 2 wks| Mon 3/4/13| Fri 3/15/13| 1. 4| Design Picnic Area| 2 wks| Mon 3/4/13| Fri 3/15/13| 1. 5| Review Landscape Overview| 1 wk| Mon 3/4/13| Fri 3/8/13| 1.

6| Design Completed| | | | . 7| Review Design with HOA| 1 wk| Mon 4/1/13| Fri 4/5/13| 1. 8| Land Inspections| 2 wks| Mon 4/8/13| Fri 4/19/13| 1. 9| Contact Utility Companies| 1 wk| Mon 4/8/13| Fri 4/12/13| 1.

10| Pricing Playground| 1 mon| Mon 4/15/13| Fri 5/10/13| 1. 11| Pricing Picnic Area| 1 mon| Mon 4/15/13| Fri 5/10/13| 1. 12| Order Playground Parts| 2 wks| Mon 5/13/13| Fri 5/24/13| 1. 13| Order Picnic Area Parts| 2 wks| Mon 5/13/13| Fri 5/24/13| 1.

14| Contact Plumber| 1 wk| Mon 5/27/13| Fri 5/31/13| 1. 15| Ordering Completed| | | | 1. 6| Schedule deliveries| 1 mon| Mon 6/3/13| Fri 6/28/13| 1. 17| Install Playground Area| 2 mons| Mon 7/1/13| Fri 8/23/13| 1. 18| Install Picnic Area| 2 mons| Mon 7/1/13| Fri 8/23/13| 1.

19| Plumber Installations| 1 wk| Mon 8/26/13| Fri 8/30/13| 1. 20| Installations Complete| | | | 1. 21| Review Playground Installations| 1 wk| Mon 9/2/13| Fri 9/6/13| 1. 22| Review Picnic Area Installations| 1 wk| Mon 9/2/13| Fri 9/6/13| 1. 23| Review Plumbing Installations| 1 wk| Mon 9/2/13| Fri 9/6/13| 1. 24| Playground and Picnic Area Installed| | | | .

25| Final Meeting with HOA Board| 5 hrs| Mon 9/9/13| Mon 9/9/13| 1. 26| Project Completed| | | | 1. 27| Project Meetings| 140 days| Fri 3/1/13| Thu 9/12/13| NETWORK DIAGRAM The Network Diagram is below to show you the view of how the tasks and subtasks breakdown so they you can view the work breakdown list in a chart basically. Risk Management Plan Project Name:| Nature’s Peace Community Playground and Picnic Area Project| Project Description Summary:| To design and build a playground and picnic area for the neighborhood.The lot is 1/2 acre of cleared land and needs to have 4-6 picnic tables and a large playground on rubber mulch with a separate area for swing sets meant for young children and adults.

| | | | | | | | | Project Manager:| Teresa Dionne| Date:| February 8, 2013| Revision Number:| 1| a. Risk Identification I have made a list of all areas that might create project delays or failures with their possible outcomes (see list below). The key risks are bolded below and appear in the Risk Management Analysis Table in section “b. 1) Delay or denial of building permits – this could cause the project to stop or require re-approvals of building and digging plans 2) Delay in utility companies coming out and marking water and power lines – this could cause a delay in setting down official plans as to layouts 3) Delay or non-availability of playground equipment being delivered – this could delay the completion of final project 4) Delay or non-availability of picnic tables delivered – this could delay the completion of the final project 5) Delay or non-availability of grill being delivered – this could delay the completion of the final project 6) Delay in design of playground layout – this could delay the start of the project 7) Delay in design of the picnic area – this could delay the start of the project 8) Delay of plumber installing fountain– this could delay the completion of the final project 9) Delay of plumber installing faucet – this could delay the completion of the final project 10) Weather delays - this could delay the installation days of the final project b. Risk Assessment The following is an assessment of these risks in terms of the probability of project occurrence and the negative cost impact of project outcomes.

Risk analysis attempts to quantify the severity of the impact of an identified risk event, sometimes the probability, and the sensitivity to change as well. Risk Scoring Matrix Defined Conditions for Risk Management Analysis| Project Objective| Relative or Numerical Scales| Very Low - 1| Low – 2| Moderate – 3| High - 4| Very High – 5| Cost| Insignificant cost increase| Less than 10% cost increase| 10-25% cost increase| 25-45% cost increase| More than 45% cost increase| Time| Insignificant time increase| Less than 5% time increase| 5-10% time increase| 10-20% time increase| More than 20% time increase| Scope| Scope decrease barely noticeable| Minor areas of scope changed| Major areas of scope changed| Scope changes not acceptable to HOA| Project no longer useful| Quality| Quality decrease barely noticeable| Less than 5% quality decrease| 5-10% quality decrease| 10-15% quality decrease| More than 15% quality decrease| RISK EVALUATION| Risk| Probability| Cost| Schedule| Scope | Quality| Risk Score|  |  |  |  |  |  |  | Delay or denial of building permits | 90%| 2| 3| 1| 4| 9. 0| Weather delays | 60%| 1| 2| 5| 1| 5. 4| Delay in utility companies coming out and marking water and power lines | 30%| 1| 4| 1| 3| 2. 7| Delay or non-availability of playground equipment being delivered | 30%| 2| 3| 1| 2| 2. | Delay or non-availability of picnic tables delivered| 30%| 2| 2| 1| 2| 2.

1| Delay or non-availability of grill being delivered| 10%| 1| 2| 1| 1| 0. 5| Delay in design of playground layout | 10%| 1| 2| 1| 1| 0. 5| Delay in design of the picnic area | 10%| 1| 2| 1| 1| 0. 5| Delay of plumber installing fountain| 10%| 1| 1| 1| 1| 0.

4| Delay of plumber installing faucet | 10%| 1| 1| 1| 1| 0. 4| c. Risk Response For each risk we have determined the action to be taken if the risk should occur: accept, shape, reduce, or transfer the risk. The following risk response table identifies a brief contingency plan for these risks.

Risk Response Matrix|Risk Event| Response*| Contingency Plan| Trigger | Person Responsible| Delay or denial of building permits | Reduce| Redo permits| Permits denied| Teresa Dionne| Weather delays | Accept| Redo schedule | Weather| Teresa Dionne| Delay in utility companies coming out and marking water and power lines | Reduce| Redo schedule | Companies delayed| Teresa Dionne| Delay or non-availability of playground equipment being delivered | Reduce| Negotiate terms with vendor| Equipment delayed| Heather True| Delay or non-availability of picnic tables delivered| Reduce| Negotiate terms with vendor| Equipment delayed| Heather True| Delay or non-availability of grill being delivered| Reduce| Negotiate terms with vendor| Equipment delayed| Heather True| Delay in design of playground layout | Reduce| Redo schedule | Delay in utility companies marking property| Cathy Newman| Delay in design of the picnic area | Reduce| Redo schedule | Delay in utility companies marking property| Cathy Newman| Delay of plumber installing fountain| Reduce| Redo schedule | Delay in utility companies marking property| Cathy Newman| Delay of plumber installing faucet | Reduce| Redo schedule | Delay in utility companies marking property| Cathy Newman| RESOURCE MANAGEMENT PLAN Final Time and Cost The above screenshot shows the cost of the time of those performing the project. The actual costs of the playground equipment and swing sets are $32,350. 00. The 4 picnic tables, outdoor grill and 2 trash cans cost $12,525. 00.

The plumber installing water fountain and faucet came to $8,320. 00 due to running the lines further into the property. Total costs = $75,866. 15. Final Time = 156 days out of 365 days from a year.

COMMUNICATION MANAGEMENT PLAN REFERENCES Erik W. Larson. Project Management w/ Project 2007 CD and Student CD, 5th Edition. McGraw-Hill Learning Solutions, 2011.