1. The following activities are part of a project to be scheduled using CPM:
Activity Immediate Predecessor Time (wks) A - 6 B A 3 C A 7 D C 2 E B,D 4 F D 3 G E,F 7 a. Draw the network b. What is the critical path? c. How many weeks will it take to complete the project? d. How much slack does activity B have? Solution b. A-C-D-E-G, also shown in the network above as the bold path. c. 26 weeks, 6+7+2+4+7. d. 6 weeks, 15-9. 2. For the project with the following information, a. Determine the critical path and the early completion time in weeks. b. Reduce the project completion time by three weeks. Assume a linear cost per week shortened, and show, step by step, how you arrived at your schedule. Solution a. A-B-D-G, 25 weeks, 5+10+6+4. b. First, reduce D (lowest cost activity on the critical path) by one week. This adds an additional critical path with activities C and E in it. Second, crash activity G by one week. Critical paths remain the same. Third, crash activity A by one week at a cost of $3,000, which is the least expensive. Summary of activities crashed: Step Activity Cost to crash Weeks reduced 1 D $1,000 1 2 G 2,000 1 3 A 3,000 1 Total cost $6,000Sorry, but downloading text is forbidden on this website.
If you need this or any other sample, we can send it to you via email.
Please, specify your valid email address
By clicking "Submit", you agree to our terms of service and privacy policy. We'll occasionally send you account related and promo emails.
Thank you!
How about make it original at only $13.90/page?
Let us edit it for you at only $13.90 to make it 100% original!
Order now