Munster Joinery is Ireland 's largest maker of energy efficient Windowss. It is located three stat mis from my house in Ireland and I spend summers working at that place during my undergrad. In 2006 Munster Joinery undertook a elaborate reappraisal of energy costs and the options that were available in diminishing their energy measure. At this clip the one-year energy use was 26 GW hours.

This reappraisal was chiefly driven by the increasing energy costs and the debut of C revenue enhancements in Ireland. As a consequence of this reappraisal the company contacted Wind Energy Direct, a company based in Limerick in Ireland that installs turbines on client 's industrial sites by agencies of a turnkey service. Due to the geographical place of the works in a vale and the high air currents that pass through that vale air current power was the logical pick for a renewable energy resource. Wind Direct operate, maintain and have full ownership of the air current turbines every bit good as financing the undertaking.

Wind Direct so sell the electricity generated to the company at a discounted rate. Wind Direct so under took a feasibleness survey, wind analysis survey and both sides proceed with the planning application. As portion of this planning application a grid application had to be applied for to the Electricity Supply Board of Ireland and was successfully granted in 2008 but due to a determination by the Commission of Energy Regulation a gate or connexion application will non be required by for about all new car production undertakings.

Two Enercon E82 2MW air current turbines were installed supplying 5 GWh per annum and giving Munster Joinery with 30 % of their energy demands.

A lesion rotor synchronal generator is used with a max velocity of 19.5 unit of ammunitions per minute. The E82 2MW air current turbine is designed for medium air current velocities and it has an 82m rotor diameter with a hub tallness between 78m and 108m. The end product is controlled by variable velocity.

This means that soap runing efficiency can be achieved without runing tonss increasing in all tonss. This besides means the quality of the extra power fed into the national grid is really good with a connexion electromotive force of 400V. The impact of the distributed coevals on the local grid should non be great. At the point of common yoke there is already a strong grid in topographic point that services that works and two towns within 2 mile radius of the works.

I have non been able to happen any demand for the support of the bing local grid from the Electricity Supply Board. The works operates from 08:00 to 17:00 Monday to Friday so extra capacity is merely available at away extremum times which is non of great benefit to the local grid. In an ideal state of affairs the mean power flow and losingss through the lines is reduced and power with proper location of the distributed coevals. In this instance the location of the distributed coevals is non the optimum distance from the substation significance losingss in the line are non kept to a lower limit.

No storage device was integrated into the design that would let supply to the works during times of low or no air currents. This means that the capacity factor of the grid has to stay the same. An added benefit of the air current turbines is that they allowed the turning away of a web ascent that would hold been needed if the works increased in size.

The foundations required for each air current turbine required about 900m3 of Earth to be removed. The size of the foundation was 16.

8m by 2.85m and required 426m3 of c30/37 concrete with 36 metric tons of steel support. Once complete they required a farther 250m3 of backfill stuff. The air current turbines where placed within the mill works which reduced transmittal costs. The turbines are non seeable from a long distance due the geographical milieus of the works. Thus the environmental impact is kept to a lower limit.



Munster Joinery now has the largest car production undertaking in the state on a commercial works ; they are now capable of selling extra capacity back into the national grid. Wind Energy stated that the two air current turbines will cut down the C emanations of the works by 9,000 metric tons per twelvemonth. The entire cost of the undertaking was ˆ6 million ; this includes all building costs of the air current turbines, planning and stuff costs. Weave Direct estimated that the energy nest eggs to Munster joinery would be over ˆ1 million over the following five old ages.

In acknowledgment of the undertakings as a presentation of what engineering is capable of in cut downing energy to all Irish concerns the Department of Communications, Energy and Natural Recourses awarded a grant of ˆ1 million to the undertaking.